Roof Permits and Home Sales in Westtown, PA
It can. Westtown Township's resale Use and Occupancy form says a seller may have to apply for permits retroactively for work done without them, and that no certificate is issued while any permit on the house is still open. A roof replacement covering 25% or more of the roof needed a permit, so settle it before you list.
We are Clear Roofing & Exteriors, roofers in West Chester, PA, and our roofing and roof replacement in Westtown page covers the roof work itself. This post is about the paperwork at sale time. Everything in it comes from Westtown Township's own forms and pages and from Pennsylvania's seller disclosure law, all read on November 18, 2026.
When does a Westtown roof replacement need a permit?
When the work covers a quarter of the roof or more. The township's Do I Need A Permit For That? flyer lists "replacement or repair of siding and/or roofing that impact 25% or more of the façade or roof area" among the projects that require a permit, and it says permits must be approved before work starts.
A few shingles lost in a windstorm sit under that line. A full roof replacement is over it every time. The flyer also says its list isn't complete and asks homeowners to call when in doubt, at 610-692-1930.
What does the resale Use and Occupancy inspection check?
Mostly life safety. Westtown's Residential Use & Occupancy Application & Inspection Checklist (revised January 2025) asks for the seller's, buyer's and seller's agent's details and says inspections must be scheduled at least two weeks before the expected settlement date. A certificate is valid for 60 days. If settlement slips past that, the house is inspected again.
The printed checklist covers smoke detectors on every level and in every bedroom, carbon monoxide detectors where there's an attached garage or fuel-burning equipment, GFCI outlets in kitchens and bathrooms, handrails, guards and plumbing leaks. The roof isn't a line on it. A roof reaches the inspection through the permit history instead.
What happens if the roof was replaced without a permit?
The same form answers it in two sentences. A Certificate of Occupancy will not be issued if there are any open permits associated with the property. And if improvements were installed or completed without the proper permits, "the seller may be required to apply for permits retroactively."
That puts the retroactive permit on the seller's clock. Westtown's Building, Zoning and Code Enforcement page says to allow 15 business days to review a permit application, which is three weeks on the calendar, and the township's third-party building code official, Code Inspections, Inc., handles the plan review and inspections. Ask the township what it will want to see for a roof that is already on, and ask before the house is listed, not after the buyer's inspection turns it up.
| Roof situation at listing | What the Westtown forms point to |
|---|---|
| Replaced with a permit, final inspection done | Nothing open. Keep the permit number with the sale papers. |
| Replaced with a permit that was never closed | An open permit. No certificate is issued until it's closed. |
| Replaced over 25% of the roof with no permit | The seller may have to apply for the permit retroactively. |
| Small repair under 25% of the roof area | Not on the flyer's permit list. Call the township if unsure. |
Does a roof permit bring in the smoke detectors too?
Sometimes. Westtown's building permit instructions say that when a permit is issued for residential alterations, repairs or additions, the entire building must have functioning smoke detectors under section 313 of the 2018 International Residential Code. Ask the township whether that applies to your roof permit. The resale checklist asks for working detectors on every level and in every bedroom either way.
Who can file the permit?
The instructions require every building permit application to include the contractor's Pennsylvania registration, or the township's Contractor Registration Form for a contractor not registered with the state, plus a certificate of insurance. A homeowner doing the work without a contractor files the township's workers' compensation form instead. Applications go to the township office, by mail or by email, per the Permits, Applications and Forms page.
If someone else did the roof, find their Pennsylvania registration number on the contract and check it in the Attorney General's Home Improvement Contractor Search. You'll want that number on the retroactive application.
What does a buyer get told about the roof?
Pennsylvania's seller disclosure law, 68 Pa.C.S. § 7304, requires the property disclosure statement to cover the roof, and separately, additions, remodeling and structural changes to the property. A closed permit, or the township's written answer that none was needed, is the paper that backs up what you write on those lines.
Before listing, pull these together: the permit number and the date of the final inspection, the roofer's contract with its registration number, and the shingle manufacturer's warranty registration. If any of it is missing, the township office is the first call.
Roof permits and selling in Westtown: frequently asked questions
Do you handle permits and inspections?
Westtown asks for a copy of the contractor's Pennsylvania registration and a certificate of insurance with every application, and a contractor already registered with the state, as we are under PA179710, doesn't need a separate township registration. Plan reviews and inspections are run by the township's third-party code official, Code Inspections, Inc.
What are the most important things to fix before selling a house?
In Westtown, start with the items on the township's resale Use and Occupancy checklist: smoke and carbon monoxide detectors, GFCI outlets in the kitchen and bathrooms, handrails and guards, and plumbing leaks. Then look for open permits or work done without one, since the form says no certificate is issued while a permit is open.
Do you need a permit to remodel a kitchen in PA?
In Westtown Township, yes when the remodel changes gas, electrical or plumbing, or the layout, such as adding or moving an island or peninsula. The township's permit flyer says replacement cabinets and countertops that match the existing size need no permit. Other municipalities draw their own lines, so ask the code office where the house sits.
How to sell a house as is in PA?
Selling as is doesn't take the house out of Westtown's resale inspection. The township's form refers to a conditional approval that can be extended for up to 90 days, so ask the township how that works when a buyer takes on the repairs. Pennsylvania's seller disclosure statement still asks about the roof.
If you're getting a Westtown house ready to sell and want the roof looked at first, call us at (484) 983-3476, 8 AM to 8 PM any day, or use the contact page.
Sources, read November 18, 2026: Westtown Township Do I Need A Permit For That? flyer, Residential Use & Occupancy Application & Inspection Checklist (rev. January 2025), Building Permit Application Instructions (rev. September 2022), Contractor Registration Form (rev. January 2026), Building, Zoning and Code Enforcement and Permits, Applications and Forms; Pennsylvania 68 Pa.C.S. § 7304; Pennsylvania Attorney General Home Improvement Contractor Search. This is general information, not legal advice. The township's current forms and code govern.